Home news Kisumu road projects at different stages as government steps up works
news

Kisumu road projects at different stages as government steps up works

Share
Share

Major road projects are at various stages of construction across Kenya’s Kisumu County, with some nearing completion while others are awaiting the start of works.

The projects include key routes linking Kisumu to neighbouring counties, as well as roads intended to improve movement within the county.

According to the Ministry of Interior and National Administration, the 30.5km Maseno-Kombewa-Kalandini road and roads in Maseno town are 67.7% complete.

The project has an estimated cost of Sh1.73 billion. The 4.7km Kisumu Boys Roundabout-Mamboleo Junction dual carriageway is further ahead, with construction 98% complete. It has cost Sh1.31illion.

Principal Secretary for Interior and National Administration Raymond Omollo said the projects were progressing at different rates.

“These projects are at different stages of implementation, but the progress shows that significant work is taking place across the county,” he said.

Roads in Kisumu are under construction to bitumen standards/Photo:Handout

The largest concentration of ongoing works is along the Mamboleo-Miwani-Chemelil-Muhoroni-Kipsitet corridor.

The 12.9km Mamboleo Junction-Miwani section, known as Lot One, is 20.2% complete and has an allocated cost of Sh5.19bn.

Lot Two, covering 43.4km between Miwani and Chemelil, is 34% complete at a cost of Sh4.96 bilion.

The 44.5km Chemelil-Muhoroni-Kipsitet section, Lot Three, is 28% complete and has an estimated cost of Sh5.72bn.

The three sections have a combined value of more than Sh15.8bn.

The corridor is expected to improve transport links between Kisumu and areas towards Kericho.

“The Mamboleo-Miwani-Chemelil-Muhoroni-Kipsitet corridor is particularly significant because of its length and the level of investment involved,” Omollo said.

Work on the Ahero and Kericho interchanges is also close to completion.

The Ahero Interchange, located at the A1/B1 junction, is 95.3% complete, while the Kericho Interchange at the B1/C23 junction is 95.2% complete.

The two projects have a combined cost of about Sh1.39 billion.
Other projects, however, remain at an earlier stage.

The 11km Koru Town-Junction C35 road and access road to Koru Bible College, valued at Sh892.6m, is listed as 11.47% complete and is currently pending.

Roads in Kisumu are under construction to bitumen standards/Photo: Handout.

Two other projects have reached the contract award stage. They are the 12km Holo-Lela Road, estimated at Sh920m, and the Chiga-Rabuor Road, with a contract value of Sh1.10 billion.

“The focus now is to ensure that projects already underway maintain momentum and that those at the contracting stage move into implementation,” Omollo said.

The government expects the road programme to improve access to markets, reduce travel times and strengthen transport links between Kisumu and neighbouring counties.

The projects could also support trade and economic activity in communities along the affected routes.

“Better roads mean better connectivity, easier movement of goods and people, and greater opportunities for communities along these routes,” Omollo said.

Share

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

CrimeFeatured

Activist demands Kisumu security chiefs to probe OCS over alleged illegal demolition

Human rights activist has accused Kisumu Central Police Station Officer Commanding Station (OCS) Chief Inspector Benson Matheka of overseeing an allegedly unlawful demolition...

CrimeFeatured

EACC recovers Sh207.7m in unexplained assets from former Trans Nzoia accountant

The Ethics and Anti-Corruption Commission (EACC) has secured a court order for the forfeiture of assets worth Sh207.7million linked to a former government...

FeaturedSports

32 nations line up for Africa Cycling Championships in Kisumu

A record 354 cyclists from 32 African countries will compete in the 2026 Africa Road Cycling Championships, which began in Kisumu on Wednesday,...

news

Kisumu county commissioner orders probe into demolition of church, ECDE centre

Kisumu County Commissioner Mohamed Ramadhan has ordered an investigation into the demolition of a church and an early childhood development education (ECDE) centre...

Politics

Siaya leaders pledge support for Ruto’s 2027 re-election bid

Siaya County leaders have pledged to support President William Ruto’s re-election bid in 2027, citing the broad-based political arrangement and development projects in...

news

Kisumu summit adopts six-point peace roadmap ahead of 2027 polls

Stakeholders at a two-day peace and leadership summit in Kisumu have adopted a six-point roadmap to strengthen security, promote inclusive governance and prevent...

Related Articles

Kisumu county commissioner orders probe into demolition of church, ECDE centre

Kisumu County Commissioner Mohamed Ramadhan has ordered an investigation into the demolition...

Kisumu summit adopts six-point peace roadmap ahead of 2027 polls

Stakeholders at a two-day peace and leadership summit in Kisumu have adopted...

PS Omollo pledges crackdown on criminals targeting Homa Bay businesses

Principal Secretary for Internal Security and National Administration Raymond Omollo has pledged...

Two killed in head-on collision along Katito-Kendu Bay Road

Two people have died following a head-on collision involving two Toyota matatus...

error: Content is protected !!